Document Processing Time Details for draft-weltman-ldapv3-auth-response

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2004-07-15 .. 2012-07-0799RFC Published-0--
2004-07-15 .. 2004-07-1509RFC Published-0--
2004-07-08 .. 2004-07-1509RFC Ed Queue-0--
2004-02-12 .. 2004-07-0809RFC Ed Queue-0--
2004-02-12 .. 2004-02-1209Approved-announcement sent-0--
2004-02-11 .. 2004-02-1209Approved-announcement sent-0--
2004-02-11 .. 2004-02-1109Approved-announcement to be sentRevised ID Needed00Authors
2003-08-21 .. 2004-02-1109Approved-announcement to be sentRevised ID Needed0175Authors
2003-08-21 .. 2003-08-2109Publication Requested-00AD
2003-08-12 .. 2003-08-2109Publication Requested-09AD
2003-04-01 .. 2003-08-1206Publication Requested-0131AD
2002-03-05 .. 2003-04-0106Publication Requested-0391Prev AD
2002-03-05 .. 2002-03-0506Publication Requested-00Prev AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2002-03-05 and was approved on 2004-02-11.

According to the speculative analysis, the document waited for AD 140 days, previous AD 391 days, authors 175 days, and others 0 days, a total of 706 days, and was revised 3 times.

The (last) responsible AD for this document was Hardie_Ted.

Overall Processing Time Statistics

Document was in individual and WG process for 934 days, and in IESG/RFC Editor process for 860 days, 1794 days in total. This is 4 years and 11 months.

Data Source

Original source data available in the tracker and draft history.