Document Processing Time Details for draft-ietf-vpim-vpimv2r2

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2004-06-30 .. 2012-07-0705RFC Published-0--
2004-06-30 .. 2004-06-3005RFC Published-0--
2002-05-07 .. 2004-06-3005RFC Ed Queue-0--
2002-05-07 .. 2002-05-0705RFC Ed Queue-0--
2002-05-07 .. 2002-05-0705Approved-announcement sent-0--
2002-04-09 .. 2002-05-0705Approved-announcement sent-0--
2002-04-04 .. 2002-04-0905IESG Evaluation-05Others
2002-04-02 .. 2002-04-0405IESG Evaluation-02Others
2002-04-02 .. 2002-04-0205AD Evaluation-00AD
2002-03-20 .. 2002-04-0205AD Evaluation-012AD
2002-03-20 .. 2002-03-2005AD Evaluation-00AD
2002-03-20 .. 2002-03-2005AD Evaluation-00AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2002-03-20 and was approved on 2002-04-09.

According to the speculative analysis, the document waited for AD 12 days, previous AD 0 days, authors 0 days, and others 7 days, a total of 19 days, and was revised 0 times.

The (last) responsible AD for this document was Freed_Ned.

Overall Processing Time Statistics

Document was in individual and WG process for 1001 days, and in IESG/RFC Editor process for 830 days, 1831 days in total. This is 5 years and 0 months.

Data Source

Original source data available in the tracker and draft history.