Document Processing Time Details for draft-ietf-v6ops-6to4-advisory

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2011-08-09 .. 2012-07-0699RFC Published-0--
2011-08-09 .. 2011-08-0902RFC Published-0--
2011-08-08 .. 2011-08-0902RFC Ed Queue-0--
2011-07-03 .. 2011-08-0802RFC Ed Queue-0--
2011-07-03 .. 2011-07-0302Approved-announcement sent-0--
2011-07-01 .. 2011-07-0302Approved-announcement sent-0--
2011-07-01 .. 2011-07-0102Approved-announcement to be sent-0--
2011-07-01 .. 2011-07-0102Approved-announcement to be sent-0--
2011-06-30 .. 2011-07-0102IESG EvaluationRevised ID Needed01Authors
2011-06-30 .. 2011-06-3002IESG EvaluationRevised ID Needed10Authors
2011-06-23 .. 2011-06-3002IESG EvaluationRevised ID Needed27Authors
2011-06-23 .. 2011-06-2302IESG EvaluationRevised ID Needed20Authors
2011-06-23 .. 2011-06-2302IESG Evaluation-20Authors
2011-06-23 .. 2011-06-2302IESG Evaluation-20Authors
2011-06-22 .. 2011-06-2301Waiting for AD Go-Ahead-21Authors
2011-06-22 .. 2011-06-2201Waiting for AD Go-Ahead-10Authors
2011-06-16 .. 2011-06-2201Waiting for AD Go-Ahead-06AD
2011-06-16 .. 2011-06-1601Waiting for AD Go-Ahead-00AD
2011-06-02 .. 2011-06-1601In Last Call-014Others
2011-06-02 .. 2011-06-0201In Last Call-00Others
2011-06-02 .. 2011-06-0201Last Call Requested-00Others
2011-06-02 .. 2011-06-0201Last Call Requested-00Others

IESG Processing Time Statistics

Document got to the AD/IESG on 2011-06-02 and was approved on 2011-07-01.

According to the speculative analysis, the document waited for AD 6 days, previous AD 0 days, authors 9 days, and others 14 days, a total of 29 days, and was revised 1 times.

The (last) responsible AD for this document was Bonica_Ron.

Overall Processing Time Statistics

Document was in individual and WG process for 120 days, and in IESG/RFC Editor process for 67 days, 187 days in total. This is 0 years and 6 months.

Data Source

Original source data available in the tracker and draft history.