Document Processing Time Details for draft-ietf-sieve-include

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2012-05-15 .. 2012-07-0615RFC Ed Queue-0--
2012-03-07 .. 2012-05-1515RFC Ed Queue-0--
2012-03-07 .. 2012-03-0715Approved-announcement sent-0--
2012-03-06 .. 2012-03-0715Approved-announcement sent-0--
2012-01-24 .. 2012-03-0614IESG EvaluationAD Followup042AD
2012-01-24 .. 2012-01-2414IESG EvaluationAD Followup10Authors
2012-01-05 .. 2012-01-2414IESG EvaluationAD Followup219Authors
2012-01-05 .. 2012-01-0514IESG EvaluationAD Followup30Authors
2012-01-05 .. 2012-01-0514IESG EvaluationAD Followup40Authors
2012-01-05 .. 2012-01-0514IESG EvaluationAD Followup40Authors
2012-01-04 .. 2012-01-0513IESG Evaluation-41Authors
2012-01-04 .. 2012-01-0413IESG Evaluation-30Authors
2011-12-31 .. 2012-01-0413IESG Evaluation-28Authors
2011-12-31 .. 2011-12-3113IESG Evaluation-10Authors
2011-12-30 .. 2011-12-3113IESG Evaluation-01Others
2011-12-30 .. 2011-12-3013IESG Evaluation-00Others
2011-12-28 .. 2011-12-3013Waiting for AD Go-Ahead-02AD
2011-12-15 .. 2011-12-2813Waiting for AD Go-Ahead-013AD
2011-12-01 .. 2011-12-1513In Last Call-014Others
2011-12-01 .. 2011-12-0113In Last Call-00Others
2011-12-01 .. 2011-12-0113Last Call Requested-00Others
2011-12-01 .. 2011-12-0113Last Call Requested-00Others
2011-11-29 .. 2011-12-0113Publication Requested-02AD
2011-11-29 .. 2011-11-2913Publication Requested-00AD
2011-04-01 .. 2011-11-2906Dead-0--
2011-01-27 .. 2011-04-0106Dead-0--
2011-01-27 .. 2011-01-2706Dead-0--
2011-01-27 .. 2011-01-2706AD is watching-0--
2010-12-20 .. 2011-01-2706AD is watching-0--

IESG Processing Time Statistics

Document got to the AD/IESG on 2011-11-29 and was approved on 2012-03-06.

According to the speculative analysis, the document waited for AD 59 days, previous AD 0 days, authors 28 days, and others 15 days, a total of 102 days, and was revised 2 times.

The (last) responsible AD for this document was Resnick_Pete.

Overall Processing Time Statistics

Document was in individual and WG process for 3149 days, and in IESG/RFC Editor process for 222 days, 3371 days in total. This is 9 years and 2 months.

Data Source

Original source data available in the tracker and draft history.