Document Processing Time Details for draft-ietf-pppext-ppp-over-aal2-class

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2002-05-08 .. 2012-07-0702RFC Ed Queue-0--
2002-05-08 .. 2002-05-0802RFC Ed Queue-0--
2002-05-02 .. 2002-05-0802IESG EvaluationRevised ID Needed06Authors
2002-04-23 .. 2002-05-0202IESG EvaluationRevised ID Needed09Authors

IESG Processing Time Statistics

Document got to the AD/IESG on 2002-04-23 and was approved on 2002-05-08.

According to the speculative analysis, the document waited for AD 0 days, previous AD 0 days, authors 15 days, and others 0 days, a total of 15 days, and was revised 0 times.

The (last) responsible AD for this document was Narten_Thomas.

Overall Processing Time Statistics

Document was in individual and WG process for 426 days, and in IESG/RFC Editor process for 3724 days, 4150 days in total. This is 11 years and 4 months.

Data Source

Original source data available in the tracker and draft history.