Document Processing Time Details for draft-ietf-ccamp-rwa-wson-framework

“End-to-End Delay from draft-smith to an RFC”

Document Timeline


IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

2011-04-26 .. 2012-07-0699RFC Published-0--
2011-04-26 .. 2011-04-2612RFC Published-0--
2011-04-25 .. 2011-04-2612RFC Ed Queue-0--
2011-02-23 .. 2011-04-2512RFC Ed Queue-0--
2011-02-23 .. 2011-02-2312Approved-announcement sent-0--
2011-02-22 .. 2011-02-2312Approved-announcement sent-0--
2011-02-17 .. 2011-02-2212Approved-announcement to be sentPoint Raised - writeup needed05AD
2011-02-17 .. 2011-02-1712Approved-announcement to be sentPoint Raised - writeup needed00AD
2011-02-15 .. 2011-02-1712IESG Evaluation-02Others
2011-02-13 .. 2011-02-1512IESG Evaluation-02Others
2011-02-08 .. 2011-02-1312Waiting for AD Go-AheadAD Followup05AD
2011-02-07 .. 2011-02-0811Waiting for AD Go-AheadAD Followup01AD
2011-02-07 .. 2011-02-0711Waiting for AD Go-AheadRevised ID Needed00Authors
2011-02-01 .. 2011-02-0710Waiting for AD Go-AheadRevised ID Needed06Authors
2011-02-01 .. 2011-02-0110Waiting for AD Go-Ahead-00AD
2011-02-01 .. 2011-02-0110Waiting for AD Go-Ahead-00AD
2011-01-18 .. 2011-02-0110In Last Call-013Others
2011-01-18 .. 2011-01-1810In Last Call-00Others
2011-01-18 .. 2011-01-1810Last Call Requested-00Others
2011-01-18 .. 2011-01-1810Last Call Requested-00Others
2011-01-18 .. 2011-01-1810AD Evaluation-00AD
2011-01-18 .. 2011-01-1810AD Evaluation-00AD
2011-01-12 .. 2011-01-1810Publication Requested-06AD
2011-01-12 .. 2011-01-1210Publication Requested-00AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2011-01-12 and was approved on 2011-02-22.

According to the speculative analysis, the document waited for AD 17 days, previous AD 0 days, authors 6 days, and others 17 days, a total of 40 days, and was revised 2 times.

The (last) responsible AD for this document was Farrel_Adrian.

Overall Processing Time Statistics

Document was in individual and WG process for 974 days, and in IESG/RFC Editor process for 104 days, 1078 days in total. This is 2 years and 11 months.

Data Source

Original source data available in the tracker and draft history.