Document Processing Time Details for draft-shafranovich-mime-csv

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2005-10-05 .. 2010-07-2299RFC Published-0--
2005-10-05 .. 2005-10-0505RFC Published-0--
2005-10-05 .. 2005-10-0506RFC Ed Queue-0--
2005-04-07 .. 2005-10-0505RFC Ed Queue-0--
2005-04-07 .. 2005-04-0705Approved-announcement sent-0--
2005-04-06 .. 2005-04-0705Approved-announcement sent-0--
2005-04-06 .. 2005-04-0605Approved-announcement to be sent-0--
2005-04-06 .. 2005-04-0605Approved-announcement to be sent-0--
2005-04-06 .. 2005-04-0605IESG EvaluationAD Followup00AD
2005-04-06 .. 2005-04-0605IESG EvaluationAD Followup10Authors
2005-04-05 .. 2005-04-0605IESG EvaluationAD Followup21Authors
2005-04-04 .. 2005-04-0504IESG EvaluationAD Followup21Authors
2005-04-04 .. 2005-04-0404IESG EvaluationRevised ID Needed20Authors
2005-03-31 .. 2005-04-0403IESG EvaluationRevised ID Needed33Authors
2005-03-31 .. 2005-03-3103IESG EvaluationRevised ID Needed40Authors
2005-03-31 .. 2005-03-3103IESG EvaluationRevised ID Needed40Authors
2005-03-31 .. 2005-03-3103IESG Evaluation-40Authors
2005-03-31 .. 2005-03-3103IESG Evaluation-30Authors
2005-03-30 .. 2005-03-3103IESG Evaluation-21Authors
2005-03-29 .. 2005-03-3003IESG Evaluation-31Authors
2005-03-28 .. 2005-03-2903IESG Evaluation-41Authors
2005-03-28 .. 2005-03-2803IESG Evaluation-30Authors
2005-03-27 .. 2005-03-2803IESG Evaluation-21Authors
2005-03-27 .. 2005-03-2703IESG Evaluation-10Authors
2005-03-22 .. 2005-03-2702IESG Evaluation-05Others
2005-03-22 .. 2005-03-2202IESG Evaluation-00Others
2005-03-22 .. 2005-03-2202Waiting for AD Go-Ahead-00AD
2005-03-21 .. 2005-03-2202Waiting for AD Go-Ahead-01AD
2005-03-21 .. 2005-03-2102In Last Call-00Others
2005-02-21 .. 2005-03-2102In Last Call-030Others
2005-02-20 .. 2005-02-2102Last Call Requested-01Others
2005-02-20 .. 2005-02-2002Last Call Requested-00Others
2005-02-20 .. 2005-02-2002AD EvaluationAD Followup00AD
2005-02-18 .. 2005-02-2002AD EvaluationAD Followup02AD
2005-02-18 .. 2005-02-1802AD EvaluationRevised ID Needed00Authors
2005-02-18 .. 2005-02-1801AD EvaluationRevised ID Needed00Authors
2005-02-18 .. 2005-02-1801AD Evaluation-00AD
2005-02-18 .. 2005-02-1801AD Evaluation-00AD
2005-02-18 .. 2005-02-1801Publication Requested-00AD
2005-02-18 .. 2005-02-1801Publication Requested-00AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2005-02-18 and was approved on 2005-04-06.

According to the speculative analysis, the document waited for AD 3 days, previous AD 0 days, authors 9 days, and others 36 days, a total of 48 days, and was revised 3 times.

The (last) responsible AD for this document was Hollenbeck_Scott.

Overall Processing Time Statistics

Document was in individual and WG process for 16 days, and in IESG/RFC Editor process for 227 days, 243 days in total. This is 0 years and 8 months.

Data Source

Original source data available in the tracker and draft history.