Document Timeline
IESG Processing
The following table shows the events relating to the document during its IESG processing.
The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.
| PERIOD | VER | STATE | SUBSTATE | DISCUSSES | DAYS | RESPONSIBLE (Speculative) |
| 2005-11-01 .. 2008-11-14 | 17 | RFC Published | - | 0 | - | - |
| 2005-11-01 .. 2005-11-01 | 16 | RFC Published | - | 0 | - | - |
| 2005-03-02 .. 2005-11-01 | 16 | RFC Ed Queue | - | 0 | - | - |
| 2005-02-24 .. 2005-03-02 | 16 | Approved-announcement sent | - | 0 | - | - |
| 2005-02-24 .. 2005-02-24 | 16 | Approved-announcement to be sent | - | 0 | - | - |
| 2005-02-24 .. 2005-02-24 | 16 | IESG Evaluation | AD Followup | 0 | 0 | AD |
| 2005-02-10 .. 2005-02-24 | 16 | IESG Evaluation | AD Followup | 1 | 14 | Authors |
| 2004-10-15 .. 2005-02-10 | 15 | IESG Evaluation | Revised ID Needed | 1 | 120 | Authors |
| 2004-10-14 .. 2004-10-15 | 15 | IESG Evaluation | - | 1 | 1 | Authors |
| 2004-10-13 .. 2004-10-14 | 15 | IESG Evaluation | - | 2 | 1 | Authors |
| 2004-10-11 .. 2004-10-13 | 15 | IESG Evaluation | - | 1 | 2 | Authors |
| 2004-09-28 .. 2004-10-11 | 15 | IESG Evaluation | - | 0 | 13 | Others |
| 2004-09-13 .. 2004-09-28 | 15 | Waiting for Writeup | - | 0 | 15 | AD |
| 2004-08-16 .. 2004-09-13 | 15 | In Last Call | - | 0 | 27 | Others |
| 2004-08-16 .. 2004-08-16 | 15 | Last Call Requested | - | 0 | 0 | Others |
| 2004-05-18 .. 2004-08-16 | 13 | Publication Requested | External Party | 0 | 88 | Others |
| 2003-04-01 .. 2004-05-18 | 10 | Publication Requested | - | 0 | 412 | AD |
| 2002-11-14 .. 2003-04-01 | 10 | Publication Requested | - | 0 | 142 | Prev AD |
IESG Processing Time Statistics
Document got to the AD/IESG on 2002-11-14 and was approved on 2005-02-24.
According to the speculative analysis, the document waited for AD 427 days, previous AD 142 days, authors 138 days, and others 128 days, a total of 835 days, and was revised 6 times.
The (last) responsible AD for this document was Hardie_Ted.
Overall Processing Time Statistics
Document was in individual and WG process for 2203 days, and in IESG/RFC Editor process for 1082 days, 3285 days in total. This is 9 years and 0 months.
Data Source
Original source data available in the tracker.
|