Document Processing Time Details for draft-kato-ipsec-ciph-camellia

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2005-12-27 .. 2010-07-2199RFC Published-0--
2005-12-27 .. 2005-12-2701RFC Published-0--
2005-12-27 .. 2005-12-2702RFC Ed Queue-0--
2005-08-04 .. 2005-12-2701RFC Ed Queue-0--
2005-08-04 .. 2005-08-0401Approved-announcement sent-0--
2005-05-16 .. 2005-08-0401Approved-announcement sent-0--
2005-05-16 .. 2005-05-1601Approved-announcement to be sentPoint Raised - writeup needed00AD
2005-05-12 .. 2005-05-1601Approved-announcement to be sentPoint Raised - writeup needed04AD
2005-05-12 .. 2005-05-1201IESG Evaluation-00Others
2005-05-12 .. 2005-05-1201IESG Evaluation-10Authors
2005-05-12 .. 2005-05-1201IESG Evaluation-20Authors
2005-05-12 .. 2005-05-1201IESG Evaluation-10Authors
2005-04-30 .. 2005-05-1201IESG Evaluation-012Others
2005-04-30 .. 2005-04-3001IESG Evaluation-00Others
2005-04-30 .. 2005-04-3001Waiting for AD Go-Ahead-00AD
2005-04-29 .. 2005-04-3001Waiting for AD Go-Ahead-01AD
2005-04-19 .. 2005-04-2901In Last Call-010Others
2005-04-01 .. 2005-04-1901In Last Call-018Others
2005-04-01 .. 2005-04-0101Last Call Requested-00Others
2005-04-01 .. 2005-04-0101In Last Call-00Others
2005-04-01 .. 2005-04-0101Last Call Requested-00Others
2005-03-31 .. 2005-04-0101In Last Call-00Others
2005-03-31 .. 2005-03-3101Last Call Requested-00Others
2005-03-31 .. 2005-03-3101Last Call Requested-00Others
2005-03-31 .. 2005-03-3101AD EvaluationAD Followup00AD
2005-03-25 .. 2005-03-3101AD EvaluationAD Followup06AD
2005-03-25 .. 2005-03-2501AD EvaluationRevised ID Needed00Authors
2005-03-06 .. 2005-03-2500AD EvaluationRevised ID Needed019Authors
2005-03-06 .. 2005-03-0600AD Evaluation-00AD
2005-03-06 .. 2005-03-0600AD Evaluation-00AD
2005-03-06 .. 2005-03-0600Publication Requested-00AD
2005-01-24 .. 2005-03-0600Publication Requested-042AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2005-01-24 and was approved on 2005-05-16.

According to the speculative analysis, the document waited for AD 53 days, previous AD 0 days, authors 19 days, and others 40 days, a total of 112 days, and was revised 1 times.

The (last) responsible AD for this document was Housley_Russ.

Overall Processing Time Statistics

Document was in individual and WG process for 23 days, and in IESG/RFC Editor process for 333 days, 356 days in total. This is 0 years and 11 months.

Data Source

Original source data available in the tracker and draft history.