Document Processing Time Details for draft-ietf-v6ops-natpt-to-historic

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2007-08-10 .. 2008-11-1401RFC Published-0--
2007-08-10 .. 2007-08-1000RFC Published-0--
2007-03-27 .. 2007-08-1000RFC Ed Queue-0--
2007-03-18 .. 2007-03-2700Approved-announcement to be sent-0--
2007-03-18 .. 2007-03-1800Approved-announcement sent-0--
2007-03-18 .. 2007-03-1800Waiting for AD Go-Ahead-00AD
2007-03-15 .. 2007-03-1800Waiting for AD Go-Ahead-13Authors
2007-03-08 .. 2007-03-1500In Last Call-17Authors
2007-02-27 .. 2007-03-0800In Last Call-011Others
2007-02-27 .. 2007-02-2700Last Call Requested-00Others
2007-02-27 .. 2007-02-2700Publication Requested-00AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2007-02-27 and was approved on 2007-03-18.

According to the speculative analysis, the document waited for AD 0 days, previous AD 0 days, authors 10 days, and others 11 days, a total of 21 days, and was revised 0 times.

The (last) responsible AD for this document was Kessens_David.

Overall Processing Time Statistics

Document was in individual and WG process for 6 days, and in IESG/RFC Editor process for 163 days, 169 days in total. This is 0 years and 5 months.

Data Source

Original source data available in the tracker.