Document Processing Time Details for draft-ietf-sipping-reg-event

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2004-04-07 .. 2008-11-1401RFC Published-0--
2004-04-07 .. 2004-04-0701RFC Published-0--
2002-12-18 .. 2004-04-0700RFC Ed Queue-0--
2002-12-16 .. 2002-12-1800Approved-announcement sent-0--
2002-12-12 .. 2002-12-1600Approved-announcement to be sent-0--
2002-12-06 .. 2002-12-1200IESG Evaluation-06Others
2002-11-07 .. 2002-12-0600In Last Call-029Others
2002-11-07 .. 2002-11-0700Last Call Requested-00Others
2002-10-31 .. 2002-11-0700Publication Requested-06AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2002-10-31 and was approved on 2002-12-12.

According to the speculative analysis, the document waited for AD 6 days, previous AD 0 days, authors 0 days, and others 35 days, a total of 41 days, and was revised 0 times.

The (last) responsible AD for this document was Mankin_Allison.

Overall Processing Time Statistics

Document was in individual and WG process for 3 days, and in IESG/RFC Editor process for 526 days, 529 days in total. This is 1 years and 5 months.

Data Source

Original source data available in the tracker.