Document Processing Time Details for draft-ietf-pilc-link-design

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2004-07-16 .. 2008-12-2499RFC Published-0--
2004-07-16 .. 2004-07-1699RFC Ed Queue-0--
2003-12-23 .. 2004-07-1699Approved-announcement sent-0--
2003-12-22 .. 2003-12-2399Approved-announcement to be sent-0--
2003-11-21 .. 2003-12-2299IESG EvaluationRevised ID Needed031Authors
2003-11-20 .. 2003-11-2199IESG Evaluation-01Others
2003-11-13 .. 2003-11-2099IESG EvaluationAD Followup07AD
2003-11-10 .. 2003-11-1399Approved-announcement to be sent-0--
2003-11-04 .. 2003-11-1099IESG EvaluationAD Followup0--
2003-06-09 .. 2003-11-0499IESG EvaluationRevised ID Needed0--
2003-04-25 .. 2003-06-0999IESG Evaluation-0--
2003-02-21 .. 2003-04-2599In Last Call-0--
2003-02-21 .. 2003-02-2199AD EvaluationRevised ID Needed0--
2002-09-20 .. 2003-02-2199AD Evaluation-0--
2002-09-20 .. 2002-09-2099Publication Requested-0--

IESG Processing Time Statistics

Document got to the AD/IESG on 2003-11-13 and was approved on 2003-12-22.

According to the speculative analysis, the document waited for AD 7 days, previous AD 0 days, authors 31 days, and others 1 days, a total of 39 days, and was revised 0 times.

The (last) responsible AD for this document was Mankin_Allison.

Overall Processing Time Statistics

Document was in individual and WG process for 1622 days, and in IESG/RFC Editor process for 248 days, 1870 days in total. This is 5 years and 1 months.

Data Source

Original source data available in the tracker.