Document Timeline
IESG Processing
The following table shows the events relating to the document during its IESG processing.
The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.
| PERIOD | VER | STATE | SUBSTATE | DISCUSSES | DAYS | RESPONSIBLE (Speculative) |
| 2008-11-24 .. 2008-12-23 | 99 | RFC Ed Queue | - | 0 | - | - |
| 2008-11-24 .. 2008-11-24 | 99 | RFC Ed Queue | - | 0 | - | - |
| 2008-11-24 .. 2008-11-24 | 99 | Approved-announcement sent | - | 0 | - | - |
| 2008-11-24 .. 2008-11-24 | 99 | IESG Evaluation | AD Followup | 0 | 0 | AD |
| 2008-11-21 .. 2008-11-24 | 99 | IESG Evaluation | AD Followup | 1 | 3 | Authors |
| 2008-11-20 .. 2008-11-21 | 99 | IESG Evaluation | AD Followup | 2 | 1 | Authors |
| 2008-11-19 .. 2008-11-20 | 99 | IESG Evaluation | Revised ID Needed | 2 | 1 | Authors |
| 2008-10-30 .. 2008-11-19 | 99 | IESG Evaluation | AD Followup | 2 | 19 | Authors |
| 2008-10-15 .. 2008-10-30 | 99 | IESG Evaluation | Revised ID Needed | 2 | 15 | Authors |
| 2008-09-04 .. 2008-10-15 | 99 | IESG Evaluation | AD Followup | 2 | 41 | Authors |
| 2008-09-01 .. 2008-09-04 | 99 | IESG Evaluation | AD Followup | 3 | 3 | Authors |
| 2008-08-19 .. 2008-09-01 | 99 | IESG Evaluation | AD Followup | 4 | 12 | Authors |
| 2008-08-19 .. 2008-08-19 | 99 | IESG Evaluation | AD Followup | 5 | 0 | Authors |
| 2008-08-19 .. 2008-08-19 | 99 | IESG Evaluation | Revised ID Needed | 5 | 0 | Authors |
| 2008-05-23 .. 2008-08-19 | 99 | IESG Evaluation | Revised ID Needed | 6 | 86 | Authors |
| 2008-05-22 .. 2008-05-23 | 99 | IESG Evaluation | - | 6 | 1 | Authors |
| 2008-05-22 .. 2008-05-22 | 99 | IESG Evaluation | - | 5 | 0 | Authors |
| 2008-05-22 .. 2008-05-22 | 99 | IESG Evaluation | - | 4 | 0 | Authors |
| 2008-05-21 .. 2008-05-22 | 99 | IESG Evaluation | - | 3 | 1 | Authors |
| 2008-05-21 .. 2008-05-21 | 99 | IESG Evaluation | - | 2 | 0 | Authors |
| 2008-05-20 .. 2008-05-21 | 99 | IESG Evaluation | - | 1 | 1 | Authors |
| 2008-05-18 .. 2008-05-20 | 99 | IESG Evaluation | - | 0 | 2 | Others |
| 2008-05-07 .. 2008-05-18 | 99 | Waiting for AD Go-Ahead | - | 0 | 11 | AD |
| 2008-04-30 .. 2008-05-07 | 99 | In Last Call | - | 0 | 7 | Others |
| 2008-04-16 .. 2008-04-30 | 99 | Last Call Requested | - | 0 | 14 | Others |
| 2008-04-16 .. 2008-04-16 | 99 | Publication Requested | AD Followup | 0 | 0 | AD |
| 2008-03-25 .. 2008-04-16 | 99 | Publication Requested | Revised ID Needed | 0 | 21 | Authors |
| 2008-03-17 .. 2008-03-25 | 99 | Publication Requested | - | 0 | 8 | AD |
IESG Processing Time Statistics
Document got to the AD/IESG on 2008-03-17 and was approved on 2008-11-24.
According to the speculative analysis, the document waited for AD 19 days, previous AD 0 days, authors 205 days, and others 23 days, a total of 247 days, and was revised 0 times.
The (last) responsible AD for this document was Callon_Ross.
Overall Processing Time Statistics
Document was in individual and WG process for 1028 days, and in IESG/RFC Editor process for 276 days, 1304 days in total. This is 3 years and 6 months.
Data Source
Original source data available in the tracker.
|