timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2005-12-27 .. 2008-12-2499RFC Published-0--
2005-12-27 .. 2005-12-2799RFC Ed Queue-0--
2005-03-30 .. 2005-12-2799Approved-announcement sent-0--
2005-03-23 .. 2005-03-3099Approved-announcement sent-0--
2005-03-07 .. 2005-03-2399Approved-announcement to be sent-0--
2005-02-22 .. 2005-03-0799IESG Evaluation-015Others
2005-02-22 .. 2005-02-2299AD EvaluationAD Followup00AD
2005-02-22 .. 2005-02-2299AD EvaluationRevised ID Needed00Authors
2004-11-12 .. 2005-02-2299AD Evaluation-0105AD
2004-09-30 .. 2004-11-1299Publication Requested-042AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2004-09-30 and was approved on 2005-03-07.

According to the speculative analysis, the document waited for AD 147 days, previous AD 0 days, authors 0 days, and others 15 days, a total of 162 days, and was revised 0 times.

The (last) responsible AD for this document was Mankin_Allison.

Overall Processing Time Statistics

Document was in individual and WG process for 729 days, and in IESG/RFC Editor process for 452 days, 1181 days in total. This is 3 years and 2 months.