| PERIOD | VER | STATE | SUBSTATE | DISCUSSES | DAYS | RESPONSIBLE (Speculative) |
| 2005-06-27 .. 2008-11-28 | 99 | RFC Published | - | 0 | - | - |
| 2005-06-27 .. 2005-06-27 | 99 | RFC Ed Queue | - | 0 | - | - |
| 2004-12-09 .. 2005-06-27 | 99 | Approved-announcement sent | - | 0 | - | - |
| 2004-12-08 .. 2004-12-09 | 99 | Approved-announcement to be sent | - | 0 | - | - |
| 2004-12-08 .. 2004-12-08 | 99 | IESG Evaluation | AD Followup | 0 | 0 | AD |
| 2004-12-08 .. 2004-12-08 | 99 | IESG Evaluation | AD Followup | 1 | 0 | Authors |
| 2004-12-08 .. 2004-12-08 | 99 | IESG Evaluation | Revised ID Needed | 1 | 0 | Authors |
| 2004-11-08 .. 2004-12-08 | 99 | IESG Evaluation | AD Followup | 1 | 30 | Authors |
| 2004-08-31 .. 2004-11-08 | 99 | IESG Evaluation - Defer | - | 1 | 67 | Authors |
| 2004-08-17 .. 2004-08-31 | 99 | IESG Evaluation - Defer | - | 0 | 14 | Others |
| 2004-08-16 .. 2004-08-17 | 99 | IESG Evaluation - Defer | - | 1 | 1 | Authors |
| 2004-08-10 .. 2004-08-16 | 99 | IESG Evaluation | - | 1 | 6 | Authors |
| 2004-08-04 .. 2004-08-10 | 99 | IESG Evaluation | - | 0 | 6 | Others |
| 2004-08-04 .. 2004-08-04 | 99 | AD Evaluation | Revised ID Needed | 0 | 0 | Authors |
| 2004-03-13 .. 2004-08-04 | 99 | AD Evaluation | - | 0 | 141 | AD |
| 2003-04-01 .. 2004-03-13 | 99 | Publication Requested | - | 0 | 347 | AD |
| 2002-10-31 .. 2003-04-01 | 99 | Publication Requested | - | 0 | 155 | Prev AD |
IESG Processing Time Statistics
Document got to the AD/IESG on 2002-10-31 and was approved on 2004-12-08.
According to the speculative analysis, the document waited for AD 488 days, previous AD 155 days, authors 104 days, and others 20 days, a total of 767 days, and was revised 0 times.
The (last) responsible AD for this document was Housley_Russ.
Overall Processing Time Statistics
Document was in individual and WG process for 4 days, and in IESG/RFC Editor process for 971 days, 975 days in total. This is 2 years and 8 months.