Document Processing Time Details for draft-ietf-mpls-te-scaling-analysis

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2008-12-15 .. 2008-12-2399RFC Ed Queue-0--
2008-12-15 .. 2008-12-1599Approved-announcement sent-0--
2008-12-15 .. 2008-12-1599Approved-announcement to be sent-0--
2008-12-14 .. 2008-12-1599IESG EvaluationAD Followup01AD
2008-12-14 .. 2008-12-1499IESG EvaluationAD Followup10Authors
2008-12-11 .. 2008-12-1499IESG Evaluation-13Authors
2008-12-03 .. 2008-12-1199IESG Evaluation-08Others
2008-12-01 .. 2008-12-0399Waiting for AD Go-Ahead-02AD
2008-11-30 .. 2008-12-0199In Last Call-01Others
2008-11-16 .. 2008-11-3099Last Call Requested-014Others
2008-08-14 .. 2008-11-1699Publication Requested-092AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2008-08-14 and was approved on 2008-12-15.

According to the speculative analysis, the document waited for AD 95 days, previous AD 0 days, authors 3 days, and others 23 days, a total of 121 days, and was revised 0 times.

The (last) responsible AD for this document was Callon_Ross.

Overall Processing Time Statistics

Document was in individual and WG process for 315 days, and in IESG/RFC Editor process for 129 days, 444 days in total. This is 1 years and 2 months.

Data Source

Original source data available in the tracker.