Document Timeline
IESG Processing
The following table shows the events relating to the document during its IESG processing.
The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.
| PERIOD | VER | STATE | SUBSTATE | DISCUSSES | DAYS | RESPONSIBLE (Speculative) |
| 2006-04-25 .. 2008-12-24 | 99 | RFC Published | - | 0 | - | - |
| 2006-04-25 .. 2006-04-25 | 99 | RFC Ed Queue | - | 0 | - | - |
| 2006-01-23 .. 2006-04-25 | 99 | Approved-announcement sent | - | 0 | - | - |
| 2006-01-18 .. 2006-01-23 | 99 | Approved-announcement to be sent | - | 0 | - | - |
| 2006-01-17 .. 2006-01-18 | 99 | IESG Evaluation | AD Followup | 0 | 1 | AD |
| 2005-12-13 .. 2006-01-17 | 99 | IESG Evaluation | AD Followup | 1 | 39 | Authors |
| 2005-11-23 .. 2005-12-13 | 99 | IESG Evaluation | - | 1 | 20 | Authors |
| 2005-10-28 .. 2005-11-23 | 99 | IESG Evaluation | - | 0 | 25 | Others |
| 2005-10-28 .. 2005-10-28 | 99 | Publication Requested | - | 0 | 0 | AD |
IESG Processing Time Statistics
Document got to the AD/IESG on 2005-10-28 and was approved on 2006-01-18.
According to the speculative analysis, the document waited for AD 1 days, previous AD 0 days, authors 59 days, and others 25 days, a total of 85 days, and was revised 0 times.
The (last) responsible AD for this document was Zinin_Alex.
Overall Processing Time Statistics
Document was in individual and WG process for 332 days, and in IESG/RFC Editor process for 182 days, 514 days in total. This is 1 years and 4 months.
Data Source
Original source data available in the tracker.
|