| PERIOD | VER | STATE | SUBSTATE | DISCUSSES | DAYS | RESPONSIBLE (Speculative) |
| 2008-12-22 .. 2008-12-23 | 99 | Approved-announcement sent | - | 0 | - | - |
| 2008-12-22 .. 2008-12-22 | 99 | Approved-announcement to be sent | - | 0 | - | - |
| 2008-12-14 .. 2008-12-22 | 99 | IESG Evaluation | - | 0 | 8 | Others |
| 2008-12-05 .. 2008-12-14 | 99 | Waiting for AD Go-Ahead | - | 0 | 9 | AD |
| 2008-12-01 .. 2008-12-05 | 99 | In Last Call | - | 0 | 4 | Others |
| 2008-11-20 .. 2008-12-01 | 99 | Last Call Requested | - | 0 | 11 | Others |
| 2008-11-20 .. 2008-11-20 | 99 | Publication Requested | - | 0 | 0 | AD |
IESG Processing Time Statistics
Document got to the AD/IESG on 2008-11-20 and was approved on 2008-12-22.
According to the speculative analysis, the document waited for AD 9 days, previous AD 0 days, authors 0 days, and others 23 days, a total of 32 days, and was revised 0 times.
The (last) responsible AD for this document was Callon_Ross.
Overall Processing Time Statistics
Document was in individual and WG process for 181 days, and in IESG/RFC Editor process for 33 days, 214 days in total. This is 0 years and 7 months.