Document Processing Time Details for draft-ietf-mobileip-ipv6

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2004-06-15 .. 2008-11-2899RFC Published-0--
2004-06-15 .. 2004-06-1599RFC Ed Queue-0--
2003-07-22 .. 2004-06-1599Approved-announcement sent-0--
2003-07-17 .. 2003-07-2299IESG EvaluationAD Followup05AD
2003-02-28 .. 2003-07-1799IESG Evaluation-0139Others
2003-02-28 .. 2003-02-2899Waiting for Writeup-00AD
2003-01-23 .. 2003-02-2899In Last Call-035Others
2003-01-23 .. 2003-01-2399IESG EvaluationRevised ID Needed00Authors
2002-06-10 .. 2003-01-2399IESG EvaluationRevised ID Needed0228Authors

IESG Processing Time Statistics

Document got to the AD/IESG on 2002-06-10 and was approved on 2003-07-22.

According to the speculative analysis, the document waited for AD 5 days, previous AD 0 days, authors 228 days, and others 174 days, a total of 407 days, and was revised 0 times.

The (last) responsible AD for this document was Narten_Thomas.

Overall Processing Time Statistics

Document was in individual and WG process for 2324 days, and in IESG/RFC Editor process for 735 days, 3059 days in total. This is 8 years and 4 months.

Data Source

Original source data available in the tracker.