Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2007-01-24 .. 2008-12-2499RFC Published-1--
2007-01-24 .. 2007-01-2499RFC Ed Queue-1--
2006-07-10 .. 2007-01-2499Approved-announcement sent-1--
2006-07-05 .. 2006-07-1099Approved-announcement to be sent-1--
2006-07-04 .. 2006-07-0599IESG EvaluationExternal Party11Authors
2006-07-04 .. 2006-07-0499IESG EvaluationExternal Party20Authors
2006-06-25 .. 2006-07-0499IESG EvaluationAD Followup29Authors
2006-06-21 .. 2006-06-2599IESG EvaluationAD Followup34Authors
2006-06-20 .. 2006-06-2199IESG EvaluationAD Followup41Authors
2006-05-16 .. 2006-06-2099IESG EvaluationRevised ID Needed434Authors
2006-03-21 .. 2006-05-1699IESG EvaluationExternal Party455Authors
2006-03-06 .. 2006-03-2199IESG EvaluationAD Followup415Authors
2006-02-19 .. 2006-03-0699IESG EvaluationAD Followup517Authors
2006-02-16 .. 2006-02-1999IESG Evaluation-53Authors
2006-02-16 .. 2006-02-1699IESG Evaluation-40Authors
2006-02-01 .. 2006-02-1699IESG Evaluation-515Authors
2006-02-01 .. 2006-02-0199IESG Evaluation-40Authors
2006-01-19 .. 2006-02-0199IESG Evaluation - Defer-412Authors
2006-01-19 .. 2006-01-1999IESG Evaluation - Defer-30Authors
2006-01-18 .. 2006-01-1999IESG EvaluationAD Followup31Authors
2006-01-18 .. 2006-01-1899IESG EvaluationAD Followup20Authors
2006-01-18 .. 2006-01-1899IESG EvaluationAD Followup10Authors
2006-01-09 .. 2006-01-1899IESG EvaluationAD Followup09AD
2005-09-27 .. 2006-01-0999IESG EvaluationRevised ID Needed0107Authors
2005-09-27 .. 2005-09-2799IESG Evaluation-00Others
2005-07-28 .. 2005-09-2799Waiting for AD Go-Ahead-059AD
2005-07-27 .. 2005-07-2899Last Call Requested-01Others
2005-07-13 .. 2005-07-2799In Last Call-014Others
2005-04-07 .. 2005-07-1399AD Evaluation-096AD
2005-04-01 .. 2005-04-0799Publication Requested-06AD
2005-03-11 .. 2005-04-0199Publication Requested-020Prev AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2005-03-11 and was approved on 2006-07-05.

According to the speculative analysis, the document waited for AD 170 days, previous AD 20 days, authors 274 days, and others 15 days, a total of 479 days, and was revised 0 times.

The (last) responsible AD for this document was Townsley_Mark.

Overall Processing Time Statistics

Document was in individual and WG process for 655 days, and in IESG/RFC Editor process for 683 days, 1338 days in total. This is 3 years and 8 months.

Data Source

Original source data available in the tracker.