Document Processing Time Details for draft-ietf-ipv6-link-scoped-mcast

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2006-05-03 .. 2008-12-2499RFC Published-1--
2006-05-03 .. 2006-05-0399RFC Ed Queue-1--
2005-08-08 .. 2006-05-0399Approved-announcement sent-1--
2005-07-28 .. 2005-08-0899Approved-announcement to be sent-1--
2005-07-27 .. 2005-07-2899Approved-announcement to be sent-1--
2005-07-27 .. 2005-07-2799IESG Evaluation-10Authors
2005-07-27 .. 2005-07-2799IESG EvaluationAD Followup10Authors
2005-07-27 .. 2005-07-2799IESG EvaluationAD Followup20Authors
2005-03-03 .. 2005-07-2799IESG EvaluationRevised ID Needed2144Authors
2005-03-03 .. 2005-03-0399IESG Evaluation-20Authors
2005-03-03 .. 2005-03-0399IESG Evaluation-10Authors
2005-02-26 .. 2005-03-0399IESG Evaluation-07Others
2005-02-22 .. 2005-02-2699Waiting for WriteupRevised ID Needed04Authors
2004-12-05 .. 2005-02-2299Waiting for WriteupExternal Party082Others
2004-12-05 .. 2004-12-0599Waiting for WriteupAD Followup00AD
2004-12-02 .. 2004-12-0599Waiting for WriteupRevised ID Needed03Authors
2004-11-17 .. 2004-12-0299Waiting for Writeup-015AD
2004-11-13 .. 2004-11-1799In Last Call-04Others
2004-10-28 .. 2004-11-1399Last Call Requested-015Others
2004-10-28 .. 2004-10-2899AD EvaluationAD Followup00AD
2004-10-15 .. 2004-10-2899AD EvaluationRevised ID Needed013Authors
2004-10-03 .. 2004-10-1599AD Evaluation-012AD
2004-09-24 .. 2004-10-0399Publication Requested-09AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2004-09-24 and was approved on 2005-07-27.

According to the speculative analysis, the document waited for AD 36 days, previous AD 0 days, authors 164 days, and others 108 days, a total of 308 days, and was revised 0 times.

The (last) responsible AD for this document was Wasserman_Margaret.

Overall Processing Time Statistics

Document was in individual and WG process for 903 days, and in IESG/RFC Editor process for 589 days, 1492 days in total. This is 4 years and 1 months.

Data Source

Original source data available in the tracker.