Document Processing Time Details for draft-ietf-ipngwg-icmp-v3

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2006-04-04 .. 2008-12-2499RFC Published-1--
2006-04-04 .. 2006-04-0499RFC Ed Queue-1--
2005-08-16 .. 2006-04-0499Approved-announcement to be sent-1--
2005-08-11 .. 2005-08-1699Approved-announcement sent-1--
2005-08-10 .. 2005-08-1199IESG EvaluationAD Followup11Authors
2005-07-28 .. 2005-08-1099IESG EvaluationAD Followup212Authors
2005-07-15 .. 2005-07-2899IESG EvaluationAD Followup313Authors
2005-07-15 .. 2005-07-1599IESG EvaluationAD Followup40Authors
2005-06-03 .. 2005-07-1599IESG EvaluationRevised ID Needed442Authors
2005-01-20 .. 2005-06-0399IESG EvaluationRevised ID Needed3133Authors
2005-01-20 .. 2005-01-2099IESG Evaluation-30Authors
2005-01-19 .. 2005-01-2099IESG Evaluation-21Authors
2005-01-19 .. 2005-01-1999IESG Evaluation-10Authors
2005-01-06 .. 2005-01-1999IESG Evaluation-013Others
2005-01-03 .. 2005-01-0699Waiting for Writeup-03AD
2005-01-02 .. 2005-01-0399In Last Call-01Others
2004-12-12 .. 2005-01-0299Last Call Requested-025Others
2004-12-09 .. 2004-12-1299Publication Requested-03AD
2004-10-22 .. 2004-12-0999AD is watchingAD Followup0--
2004-06-03 .. 2004-10-2299AD is watchingRevised ID Needed0--
2003-08-01 .. 2004-06-0399AD is watching-0--
2003-06-23 .. 2003-08-0199AD is watching-0--
2003-06-23 .. 2003-06-2399AD EvaluationRevised ID Needed0--
2002-06-11 .. 2003-06-2399IESG EvaluationRevised ID Needed0--
2002-06-11 .. 2002-06-1199Publication Requested-0--

IESG Processing Time Statistics

Document got to the AD/IESG on 2004-12-09 and was approved on 2005-08-11.

According to the speculative analysis, the document waited for AD 6 days, previous AD 0 days, authors 202 days, and others 39 days, a total of 247 days, and was revised 0 times.

The (last) responsible AD for this document was Wasserman_Margaret.

Overall Processing Time Statistics

Document was in individual and WG process for 1989 days, and in IESG/RFC Editor process for 485 days, 2474 days in total. This is 6 years and 9 months.

Data Source

Original source data available in the tracker.