| PERIOD | VER | STATE | SUBSTATE | DISCUSSES | DAYS | RESPONSIBLE (Speculative) |
| 2006-08-10 .. 2010-07-22 | 99 | RFC Published | - | 0 | - | - |
| 2006-08-10 .. 2006-08-10 | 15 | RFC Published | - | 0 | - | - |
| 2006-08-10 .. 2006-08-10 | 15 | RFC Ed Queue | - | 0 | - | - |
| 2006-03-23 .. 2006-08-10 | 15 | RFC Ed Queue | - | 0 | - | - |
| 2006-03-23 .. 2006-03-23 | 15 | Approved-announcement sent | - | 0 | - | - |
| 2006-03-13 .. 2006-03-23 | 15 | Approved-announcement sent | - | 0 | - | - |
| 2006-03-13 .. 2006-03-13 | 15 | Approved-announcement to be sent | - | 0 | - | - |
| 2006-03-12 .. 2006-03-13 | 15 | Approved-announcement to be sent | - | 0 | - | - |
| 2006-03-12 .. 2006-03-12 | 15 | IESG Evaluation | AD Followup | 0 | 0 | AD |
| 2006-03-10 .. 2006-03-12 | 15 | IESG Evaluation | AD Followup | 1 | 2 | Authors |
| 2006-03-03 .. 2006-03-10 | 15 | IESG Evaluation | AD Followup | 2 | 7 | Authors |
| 2006-03-02 .. 2006-03-03 | 15 | IESG Evaluation | AD Followup | 2 | 1 | Authors |
| 2006-03-01 .. 2006-03-02 | 15 | IESG Evaluation | - | 2 | 1 | Authors |
| 2006-03-01 .. 2006-03-01 | 15 | IESG Evaluation | - | 1 | 0 | Authors |
| 2006-03-01 .. 2006-03-01 | 15 | IESG Evaluation | - | 0 | 0 | Others |
| 2006-03-01 .. 2006-03-01 | 15 | IESG Evaluation | - | 1 | 0 | Authors |
| 2006-02-17 .. 2006-03-01 | 15 | IESG Evaluation | - | 2 | 14 | Authors |
| 2006-02-17 .. 2006-02-17 | 15 | IESG Evaluation | - | 2 | 0 | Authors |
| 2006-02-17 .. 2006-02-17 | 15 | AD Evaluation | - | 2 | 0 | Authors |
| 2006-02-17 .. 2006-02-17 | 15 | AD Evaluation | - | 2 | 0 | Authors |
| 2005-08-17 .. 2006-02-17 | 12 | AD is watching | AD Followup | 2 | - | - |
| 2005-08-17 .. 2005-08-17 | 12 | AD is watching | AD Followup | 1 | - | - |
| 2005-08-17 .. 2005-08-17 | 12 | AD is watching | AD Followup | 0 | - | - |
| 2005-07-14 .. 2005-08-17 | 12 | AD is watching | AD Followup | 0 | - | - |
| 2003-08-01 .. 2005-07-14 | 09 | AD is watching | Revised ID Needed | 0 | - | - |
| 2003-06-23 .. 2003-08-01 | 09 | AD is watching | Revised ID Needed | 0 | - | - |
| 2003-06-23 .. 2003-06-23 | 09 | AD is watching | Revised ID Needed | 0 | - | - |
| 2003-06-23 .. 2003-06-23 | 09 | IESG Evaluation | Revised ID Needed | 0 | - | - |
| 2002-10-04 .. 2003-06-23 | 09 | IESG Evaluation | Revised ID Needed | 0 | - | - |
| 2002-06-14 .. 2002-10-04 | 09 | IESG Evaluation | Revised ID Needed | 0 | - | - |
| 2002-06-14 .. 2002-06-14 | 09 | Evaluation | Revised ID Needed | 0 | - | - |
| 2002-06-14 .. 2002-06-14 | 09 | IESG Evaluation | - | 0 | - | - |
| 2002-06-09 .. 2002-06-14 | 09 | IESG Evaluation | - | 0 | - | - |
| 2002-05-23 .. 2002-06-09 | 09 | In Last Call | - | 0 | - | - |
| 2002-05-23 .. 2002-05-23 | 09 | In Last Call | - | 0 | - | - |
| 2002-04-23 .. 2002-05-23 | 08 | IESG Evaluation | Revised ID Needed | 0 | - | - |
| 2002-04-23 .. 2002-04-23 | 08 | IESG Evaluation | Revised ID Needed | 0 | - | - |
IESG Processing Time Statistics
Document got to the AD/IESG on 2006-02-17 and was approved on 2006-03-12.
According to the speculative analysis, the document waited for AD 0 days, previous AD 0 days, authors 25 days, and others 0 days, a total of 25 days, and was revised 0 times.
The (last) responsible AD for this document was Wasserman_Margaret.
Overall Processing Time Statistics
Document was in individual and WG process for 3127 days, and in IESG/RFC Editor process for 173 days, 3300 days in total. This is 9 years and 0 months.