Document Processing Time Details for draft-ietf-ipcdn-device-mibv2

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2007-01-02 .. 2008-12-2499RFC Published-0--
2006-04-01 .. 2007-01-0299RFC Ed Queue-0--
2006-03-30 .. 2006-04-0199RFC Ed Queue-0--
2006-03-28 .. 2006-03-3099Approved-announcement sent-0--
2006-03-21 .. 2006-03-2899Approved-announcement to be sent-0--
2006-03-13 .. 2006-03-2199IESG Evaluation-08Others
2005-12-29 .. 2006-03-1399Waiting for AD Go-AheadExternal Party079Others
2005-12-28 .. 2005-12-2999Waiting for AD Go-Ahead-01Prev AD
2005-12-14 .. 2005-12-2899In Last Call-014Others
2005-12-14 .. 2005-12-1499Last Call Requested-00Others
2005-12-14 .. 2005-12-1499Publication Requested-00Prev AD
2005-11-25 .. 2005-12-1499AD is watchingAD Followup0--
2005-10-26 .. 2005-11-2599AD is watchingRevised ID Needed0--
2005-08-16 .. 2005-10-2699AD is watching-0--

IESG Processing Time Statistics

Document got to the AD/IESG on 2005-12-14 and was approved on 2006-03-21.

According to the speculative analysis, the document waited for AD 0 days, previous AD 1 days, authors 0 days, and others 101 days, a total of 102 days, and was revised 0 times.

The (last) responsible AD for this document was Romascanu_Dan.

Overall Processing Time Statistics

Document was in individual and WG process for 1969 days, and in IESG/RFC Editor process for 388 days, 2357 days in total. This is 6 years and 5 months.

Data Source

Original source data available in the tracker.