Document Processing Time Details for draft-ietf-imss-fc-rscn-mib

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2007-08-27 .. 2008-12-2499RFC Published-0--
2007-08-27 .. 2007-08-2799RFC Ed Queue-0--
2007-03-14 .. 2007-08-2799Approved-announcement sent-0--
2007-03-12 .. 2007-03-1499Approved-announcement to be sent-0--
2007-03-02 .. 2007-03-1299IESG Evaluation-010Others
2007-03-01 .. 2007-03-0299Waiting for Writeup-01AD
2007-02-19 .. 2007-03-0199In Last Call-012Others
2007-02-05 .. 2007-02-1999Last Call Requested-014Others
2007-01-25 .. 2007-02-0599Publication Requested-010AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2007-01-25 and was approved on 2007-03-12.

According to the speculative analysis, the document waited for AD 11 days, previous AD 0 days, authors 0 days, and others 36 days, a total of 47 days, and was revised 0 times.

The (last) responsible AD for this document was Romascanu_Dan.

Overall Processing Time Statistics

Document was in individual and WG process for 427 days, and in IESG/RFC Editor process for 212 days, 639 days in total. This is 1 years and 9 months.