Document Processing Time Details for draft-ietf-idr-rfc2858bis

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2007-01-24 .. 2010-07-2299RFC Published-0--
2007-01-24 .. 2007-01-2410RFC Published-0--
2006-07-24 .. 2007-01-2410RFC Ed Queue-0--
2006-06-19 .. 2006-07-2410RFC Ed Queue-0--
2006-06-19 .. 2006-06-1910Approved-announcement sent-0--
2006-06-12 .. 2006-06-1910Approved-announcement sent-0--
2006-06-12 .. 2006-06-1210Approved-announcement to be sent-0--
2006-05-11 .. 2006-06-1210Approved-announcement to be sent-0--
2006-05-11 .. 2006-05-1110Approved-announcement to be sentPoint Raised - writeup needed00AD
2006-05-11 .. 2006-05-1110Approved-announcement to be sentPoint Raised - writeup needed00AD
2006-05-10 .. 2006-05-1110IESG Evaluation-01Others
2006-05-09 .. 2006-05-1010IESG Evaluation-11Authors
2006-05-04 .. 2006-05-0910IESG Evaluation-05Others
2006-05-04 .. 2006-05-0410IESG Evaluation-00Others
2006-03-06 .. 2006-05-0409IESG EvaluationAD Followup058AD
2006-01-27 .. 2006-03-0608IESG EvaluationAD Followup039AD
2006-01-23 .. 2006-01-2707IESG EvaluationRevised ID Needed04Authors
2006-01-23 .. 2006-01-2307IESG EvaluationRevised ID Needed00Authors
2006-01-23 .. 2006-01-2307IESG EvaluationAD Followup00AD
2006-01-23 .. 2006-01-2307IESG EvaluationAD Followup10Authors
2006-01-23 .. 2006-01-2307IESG EvaluationAD Followup20Authors
2005-12-01 .. 2006-01-2307IESG EvaluationAD Followup257Authors
2005-12-01 .. 2005-12-0107IESG Evaluation-20Authors
2005-12-01 .. 2005-12-0107IESG Evaluation-10Authors
2005-12-01 .. 2005-12-0107IESG Evaluation-00Others
2005-12-01 .. 2005-12-0107IESG Evaluation--10Others
2005-11-22 .. 2005-12-0107IESG Evaluation--29Others
2005-11-02 .. 2005-11-2207IESG Evaluation--220Others
2005-11-02 .. 2005-11-0207Waiting for AD Go-Ahead--20AD
2005-10-07 .. 2005-11-0207Waiting for AD Go-Ahead--225AD
2005-10-07 .. 2005-10-0707In Last Call--20Others
2005-09-23 .. 2005-10-0707In Last Call--214Others
2005-09-22 .. 2005-09-2307Last Call Requested--21Others
2005-09-22 .. 2005-09-2207Last Call Requested--20Others
2005-09-22 .. 2005-09-2207AD Evaluation--20AD
2005-08-30 .. 2005-09-2207AD Evaluation--222AD
2004-08-31 .. 2005-08-3006Publication Requested--2364AD
2004-07-23 .. 2004-08-3106Publication Requested--238AD
2004-05-25 .. 2004-07-2306Publication Requested--258AD
2004-01-21 .. 2004-05-2504Publication Requested--2124AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2004-01-21 and was approved on 2006-05-11.

According to the speculative analysis, the document waited for AD 728 days, previous AD 0 days, authors 62 days, and others 50 days, a total of 840 days, and was revised 6 times.

The (last) responsible AD for this document was Fenner_Bill.

Overall Processing Time Statistics

Document was in individual and WG process for 743 days, and in IESG/RFC Editor process for 1098 days, 1841 days in total. This is 5 years and 0 months.

Data Source

Original source data available in the tracker and draft history.