Document Processing Time Details for draft-ietf-idr-rfc2796bis

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2006-05-02 .. 2008-12-2499RFC Published-0--
2006-05-02 .. 2006-05-0299RFC Ed Queue-0--
2006-01-26 .. 2006-05-0299Approved-announcement sent-0--
2006-01-25 .. 2006-01-2699Approved-announcement to be sent-0--
2006-01-24 .. 2006-01-2599IESG EvaluationAD Followup01AD
2006-01-12 .. 2006-01-2499IESG EvaluationAD Followup112Authors
2005-12-21 .. 2006-01-1299IESG EvaluationAD Followup226Authors
2005-10-12 .. 2005-12-2199IESG EvaluationAD Followup369Authors
2005-09-29 .. 2005-10-1299IESG Evaluation-313Authors
2005-09-27 .. 2005-09-2999IESG Evaluation-22Authors
2005-09-26 .. 2005-09-2799IESG Evaluation-11Authors
2005-09-26 .. 2005-09-2699IESG Evaluation-00Others
2005-09-08 .. 2005-09-2699Waiting for Writeup-018AD
2005-09-05 .. 2005-09-0899In Last Call-03Others
2005-08-22 .. 2005-09-0599Last Call Requested-013Others
2005-08-15 .. 2005-08-2299Publication Requested-07AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2005-08-15 and was approved on 2006-01-25.

According to the speculative analysis, the document waited for AD 26 days, previous AD 0 days, authors 123 days, and others 16 days, a total of 165 days, and was revised 0 times.

The (last) responsible AD for this document was Fenner_Bill.

Overall Processing Time Statistics

Document was in individual and WG process for 529 days, and in IESG/RFC Editor process for 262 days, 791 days in total. This is 2 years and 2 months.

Data Source

Original source data available in the tracker.