Document Processing Time Details for draft-ietf-idr-bgp4

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2006-01-17 .. 2008-11-2899RFC Published-1--
2006-01-17 .. 2006-01-1799RFC Published-1--
2005-08-08 .. 2006-01-1799RFC Ed Queue-1--
2005-01-31 .. 2005-08-0899Approved-announcement sent-1--
2005-01-31 .. 2005-01-3199Approved-announcement to be sent-1--
2005-01-28 .. 2005-01-3199Approved-announcement to be sentPoint Raised - writeup needed13Authors
2004-12-02 .. 2005-01-2899IESG Evaluation-161Authors
2004-12-01 .. 2004-12-0299IESG Evaluation-21Authors
2004-11-28 .. 2004-12-0199IESG Evaluation-33Authors
2004-11-28 .. 2004-11-2899IESG Evaluation-20Authors
2004-11-23 .. 2004-11-2899IESG Evaluation-35Authors
2004-10-22 .. 2004-11-2399IESG EvaluationAD Followup331Authors
2004-09-16 .. 2004-10-2299IESG EvaluationAD Followup436Authors
2004-09-13 .. 2004-09-1699IESG EvaluationRevised ID Needed43Authors
2004-07-22 .. 2004-09-1399IESG Evaluation-451Authors
2004-07-21 .. 2004-07-2299IESG Evaluation-31Authors
2004-07-21 .. 2004-07-2199IESG Evaluation-20Authors
2004-07-21 .. 2004-07-2199IESG Evaluation-10Authors
2004-07-21 .. 2004-07-2199IESG Evaluation-20Authors
2004-07-21 .. 2004-07-2199IESG Evaluation-10Authors
2004-07-20 .. 2004-07-2199IESG Evaluation-01Others
2004-07-15 .. 2004-07-2099Waiting for AD Go-AheadAD Followup05AD
2004-06-17 .. 2004-07-1599Waiting for AD Go-AheadRevised ID Needed028Authors
2004-04-16 .. 2004-06-1799Waiting for Writeup-061AD
2004-04-13 .. 2004-04-1699In Last Call-03Others
2004-03-16 .. 2004-04-1399Last Call Requested-027Others
2003-05-22 .. 2004-03-1699AD EvaluationRevised ID Needed0299Authors
2003-04-01 .. 2003-05-2299AD Evaluation-051AD
2003-03-11 .. 2003-04-0199Publication Requested-020AD
2003-03-11 .. 2003-03-1199Publication Requested-00AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2003-03-11 and was approved on 2005-01-31.

According to the speculative analysis, the document waited for AD 137 days, previous AD 0 days, authors 522 days, and others 31 days, a total of 690 days, and was revised 0 times.

The (last) responsible AD for this document was Zinin_Alex.

Overall Processing Time Statistics

Document was in individual and WG process for 2840 days, and in IESG/RFC Editor process for 1041 days, 3881 days in total. This is 10 years and 7 months.

Data Source

Original source data available in the tracker.