IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2006-01-17 .. 2008-12-2499RFC Published-1--
2006-01-17 .. 2006-01-1799RFC Published-1--
2006-01-17 .. 2006-01-1799RFC Ed Queue-1--
2005-01-31 .. 2006-01-1799Approved-announcement sent-1--
2005-01-31 .. 2005-01-3199Approved-announcement to be sent-1--
2005-01-28 .. 2005-01-3199Approved-announcement to be sentPoint Raised - writeup needed13Authors
2004-12-01 .. 2005-01-2899IESG Evaluation-162Authors
2004-12-01 .. 2004-12-0199IESG Evaluation-20Authors
2004-11-29 .. 2004-12-0199IESG Evaluation-32Authors
2004-11-28 .. 2004-11-2999IESG Evaluation-21Authors
2004-11-23 .. 2004-11-2899IESG Evaluation-35Authors
2004-11-23 .. 2004-11-2399IESG EvaluationAD Followup30Authors
2004-11-11 .. 2004-11-2399IESG EvaluationRevised ID Needed312Authors
2004-09-16 .. 2004-11-1199IESG EvaluationRevised ID Needed455Authors
2004-07-22 .. 2004-09-1699IESG Evaluation-454Authors
2004-07-22 .. 2004-07-2299IESG Evaluation-30Authors
2004-07-21 .. 2004-07-2299IESG Evaluation-21Authors
2004-07-21 .. 2004-07-2199IESG Evaluation-10Authors
2004-07-21 .. 2004-07-2199IESG Evaluation-20Authors
2004-07-21 .. 2004-07-2199IESG Evaluation-10Authors
2004-07-20 .. 2004-07-2199IESG Evaluation-01Others
2004-07-15 .. 2004-07-2099Waiting for AD Go-AheadAD Followup05AD
2004-07-12 .. 2004-07-1599Waiting for AD Go-AheadRevised ID Needed03Authors
2004-04-16 .. 2004-07-1299Waiting for Writeup-086AD
2004-04-13 .. 2004-04-1699In Last Call-03Others
2004-03-16 .. 2004-04-1399Last Call Requested-027Others
2004-03-16 .. 2004-03-1699Publication Requested-00AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2004-03-16 and was approved on 2005-01-31.

According to the speculative analysis, the document waited for AD 91 days, previous AD 0 days, authors 198 days, and others 31 days, a total of 320 days, and was revised 0 times.

The (last) responsible AD for this document was Zinin_Alex.

Overall Processing Time Statistics

Document was in individual and WG process for 45 days, and in IESG/RFC Editor process for 671 days, 716 days in total. This is 1 years and 11 months.

Data Source

Original source data available in the tracker.