Document Processing Time Details for draft-ietf-idr-as-documentation-reservation

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2008-12-11 .. 2008-12-2499RFC Published-0--
2008-12-11 .. 2008-12-1199RFC Ed Queue-0--
2008-11-10 .. 2008-12-1199Approved-announcement sent-0--
2008-11-10 .. 2008-11-1099Approved-announcement to be sent-0--
2008-11-06 .. 2008-11-1099Waiting for AD Go-Ahead-04AD
2008-11-06 .. 2008-11-0699In Last Call-00Others
2008-11-05 .. 2008-11-0699In Last Call-11Authors
2008-10-23 .. 2008-11-0599In Last Call-012Others
2008-10-23 .. 2008-10-2399Last Call Requested-00Others

IESG Processing Time Statistics

Document got to the AD/IESG on 2008-10-23 and was approved on 2008-11-10.

According to the speculative analysis, the document waited for AD 4 days, previous AD 0 days, authors 1 days, and others 12 days, a total of 17 days, and was revised 0 times.

The (last) responsible AD for this document was Ward_David.

Overall Processing Time Statistics

Document was in individual and WG process for 19 days, and in IESG/RFC Editor process for 48 days, 67 days in total. This is 0 years and 2 months.

Data Source

Original source data available in the tracker.