The following table shows the events relating to the document during its IESG processing.
The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.
| PERIOD | VER | STATE | SUBSTATE | DISCUSSES | DAYS | RESPONSIBLE (Speculative) |
| 2002-09-30 .. 2010-07-22 | 08 | RFC Published | - | 0 | - | - |
| 2002-09-30 .. 2002-09-30 | 08 | RFC Published | - | 0 | - | - |
| 2002-09-30 .. 2002-09-30 | 08 | Publication Requested | - | 0 | 0 | AD |
| 2002-06-09 .. 2002-09-30 | 08 | Publication Requested | - | 0 | 111 | AD |
IESG Processing Time Statistics
Document got to the AD/IESG on 2002-06-09 and was approved on 2002-09-30.
According to the speculative analysis, the document waited for AD 111 days, previous AD 0 days, authors 0 days, and others 0 days, a total of 111 days, and was revised 0 times.
The (last) responsible AD for this document was Freed_Ned.
Overall Processing Time Statistics
Document was in individual and WG process for 963 days, and in IESG/RFC Editor process for 111 days, 1074 days in total. This is 2 years and 11 months.
Data Source
Original source data available in the tracker and draft history.
|