Document Processing Time Details for draft-ietf-enum-softswitch-req

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2008-10-06 .. 2008-12-2499RFC Published-0--
2008-10-06 .. 2008-10-0699RFC Ed Queue-0--
2008-08-28 .. 2008-10-0699Approved-announcement sent-0--
2008-08-28 .. 2008-08-2899IESG EvaluationAD Followup00AD
2008-07-17 .. 2008-08-2899IESG EvaluationAD Followup141Authors
2008-07-09 .. 2008-07-1799IESG EvaluationAD Followup28Authors
2008-07-09 .. 2008-07-0999IESG EvaluationRevised ID Needed20Authors
2008-07-03 .. 2008-07-0999IESG Evaluation-26Authors
2008-07-02 .. 2008-07-0399IESG Evaluation-11Authors
2008-06-26 .. 2008-07-0299IESG Evaluation-06Others
2008-06-11 .. 2008-06-2699Waiting for AD Go-Ahead-015AD
2008-05-27 .. 2008-06-1199In Last Call-014Others
2008-05-14 .. 2008-05-2799Last Call Requested-013Others
2008-05-14 .. 2008-05-1499AD EvaluationRevised ID Needed00Authors
2008-04-28 .. 2008-05-1499AD Evaluation-016AD
2008-04-08 .. 2008-04-2899Publication Requested-020AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2008-04-08 and was approved on 2008-08-28.

According to the speculative analysis, the document waited for AD 51 days, previous AD 0 days, authors 56 days, and others 33 days, a total of 140 days, and was revised 0 times.

The (last) responsible AD for this document was Peterson_Jon.

Overall Processing Time Statistics

Document was in individual and WG process for 343 days, and in IESG/RFC Editor process for 178 days, 521 days in total. This is 1 years and 5 months.

Data Source

Original source data available in the tracker.