Document Processing Time Details for draft-ietf-enum-pstn

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2006-12-04 .. 2010-07-2299RFC Published-0--
2006-12-04 .. 2006-12-0405RFC Published-0--
2006-12-04 .. 2006-12-0405RFC Ed Queue-0--
2006-10-03 .. 2006-12-0405RFC Ed Queue-0--
2006-10-03 .. 2006-10-0305Approved-announcement sent-0--
2006-09-28 .. 2006-10-0305Approved-announcement sent-0--
2006-09-28 .. 2006-09-2805Approved-announcement to be sent-0--
2006-09-28 .. 2006-09-2805Approved-announcement to be sent-0--
2006-09-28 .. 2006-09-2805IESG EvaluationAD Followup00AD
2006-09-22 .. 2006-09-2805IESG EvaluationAD Followup16Authors
2006-09-22 .. 2006-09-2205IESG EvaluationAD Followup20Authors
2006-08-08 .. 2006-09-2205IESG EvaluationAD Followup344Authors
2006-08-07 .. 2006-08-0805IESG EvaluationAD Followup41Authors
2006-06-22 .. 2006-08-0704IESG EvaluationAD Followup445Authors
2006-06-22 .. 2006-06-2204IESG Evaluation-40Authors
2006-06-22 .. 2006-06-2204IESG Evaluation-30Authors
2006-06-21 .. 2006-06-2204IESG Evaluation-21Authors
2006-06-21 .. 2006-06-2104IESG Evaluation-20Authors
2006-06-20 .. 2006-06-2104Waiting for Writeup-21Authors
2006-06-20 .. 2006-06-2004Waiting for Writeup-10Authors
2006-06-15 .. 2006-06-2004Waiting for Writeup-05AD
2006-06-01 .. 2006-06-1504Waiting for Writeup-014AD
2006-06-01 .. 2006-06-0104In Last Call-00Others
2006-05-18 .. 2006-06-0104In Last Call-013Others
2006-05-18 .. 2006-05-1804Last Call Requested-00Others
2006-05-18 .. 2006-05-1804Last Call Requested-00Others
2006-05-18 .. 2006-05-1804AD EvaluationAD Followup00AD
2006-05-10 .. 2006-05-1804AD EvaluationAD Followup08AD
2006-05-10 .. 2006-05-1004AD EvaluationRevised ID Needed00Authors
2006-05-02 .. 2006-05-1003AD EvaluationRevised ID Needed08Authors
2006-02-17 .. 2006-05-0203AD Evaluation-075AD
2006-02-17 .. 2006-02-1703AD Evaluation-00AD
2006-02-17 .. 2006-02-1703Publication Requested-00AD
2006-02-07 .. 2006-02-1703Publication Requested-010AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2006-02-07 and was approved on 2006-09-28.

According to the speculative analysis, the document waited for AD 112 days, previous AD 0 days, authors 106 days, and others 13 days, a total of 231 days, and was revised 2 times.

The (last) responsible AD for this document was Peterson_Jon.

Overall Processing Time Statistics

Document was in individual and WG process for 104 days, and in IESG/RFC Editor process for 297 days, 401 days in total. This is 1 years and 1 months.

Data Source

Original source data available in the tracker and draft history.