Document Processing Time Details for draft-ietf-dnsext-mdns

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2007-02-01 .. 2008-11-2899RFC Published-0--
2007-02-01 .. 2007-02-0199RFC Ed Queue-0--
2006-11-01 .. 2007-02-0199Approved-announcement sent-0--
2006-08-21 .. 2006-11-0199Approved-announcement to be sentExternal Party070Others
2006-08-21 .. 2006-08-2199Approved-announcement to be sentPoint Raised - writeup needed00AD
2006-07-20 .. 2006-08-2199IESG Evaluation-031Others
2006-07-20 .. 2006-07-2099IESG Evaluation-10Authors
2006-07-19 .. 2006-07-2099IESG Evaluation-21Authors
2006-07-14 .. 2006-07-1999IESG Evaluation - Defer-25Authors
2006-07-06 .. 2006-07-1499IESG Evaluation-28Authors
2006-07-05 .. 2006-07-0699IESG Evaluation-11Authors
2006-06-30 .. 2006-07-0599IESG Evaluation-05Others
2006-06-19 .. 2006-06-3099AD Evaluation-011AD
2006-05-17 .. 2006-06-1999Publication Requested-032AD
2005-10-03 .. 2006-05-1799AD is watching-0--
2005-09-19 .. 2005-10-0399Waiting for AD Go-AheadAD Followup0--
2005-08-31 .. 2005-09-1999Waiting for AD Go-AheadRevised ID Needed0--
2005-08-25 .. 2005-08-3199Waiting for AD Go-Ahead-0--
2005-08-24 .. 2005-08-2599Last Call Requested-0--
2005-08-10 .. 2005-08-2499In Last Call-0--
2005-08-08 .. 2005-08-1099AD EvaluationAD Followup0--
2005-07-18 .. 2005-08-0899AD EvaluationRevised ID Needed0--
2005-04-01 .. 2005-07-1899AD EvaluationAD Followup0--
2005-03-11 .. 2005-04-0199AD EvaluationAD Followup0--
2005-02-21 .. 2005-03-1199AD EvaluationRevised ID Needed0--
2004-09-08 .. 2005-02-2199AD Evaluation-0--
2004-08-27 .. 2004-09-0899Publication Requested-0--

IESG Processing Time Statistics

Document got to the AD/IESG on 2006-05-17 and was approved on 2006-11-01.

According to the speculative analysis, the document waited for AD 43 days, previous AD 0 days, authors 15 days, and others 106 days, a total of 164 days, and was revised 0 times.

The (last) responsible AD for this document was Townsley_Mark.

Overall Processing Time Statistics

Document was in individual and WG process for 2258 days, and in IESG/RFC Editor process for 259 days, 2517 days in total. This is 6 years and 10 months.

Data Source

Original source data available in the tracker.