Document Processing Time Details for draft-ietf-atommib-rfc2493bis

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2003-09-04 .. 2010-03-1201RFC Published-0--
2003-09-04 .. 2003-09-0401RFC Ed Queue-0--
2003-04-10 .. 2003-09-0401Approved-announcement sent-0--
2003-04-08 .. 2003-04-1001Approved-announcement to be sent-0--
2003-04-08 .. 2003-04-0801IESG Evaluation-00Others
2003-03-28 .. 2003-04-0801Waiting for Writeup-010AD
2003-02-04 .. 2003-03-2801In Last Call-054Others
2003-02-04 .. 2003-02-0401AD Evaluation-00AD
2003-01-24 .. 2003-02-0400AD is watching-0--
2002-10-22 .. 2003-01-2400AD is watching-0--
2002-09-25 .. 2002-10-2200AD EvaluationExternal Party0--
2002-08-20 .. 2002-09-2500IESG EvaluationRevised ID Needed0--
2002-08-20 .. 2002-08-2000Publication Requested-0--

IESG Processing Time Statistics

Document got to the AD/IESG on 2003-02-04 and was approved on 2003-04-08.

According to the speculative analysis, the document waited for AD 10 days, previous AD 0 days, authors 0 days, and others 54 days, a total of 64 days, and was revised 0 times.

The (last) responsible AD for this document was Nordmark_Erik.

Overall Processing Time Statistics

Document was in individual and WG process for 351 days, and in IESG/RFC Editor process for 210 days, 561 days in total. This is 1 years and 6 months.

Data Source

Original source data available in the tracker and draft history.