Document Processing Time Details for draft-ietf-appsawg-mime-default-charset

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2012-04-23 .. 2012-05-0403In Last Call-011Others
2012-04-23 .. 2012-04-2303In Last Call-00Others
2012-04-21 .. 2012-04-2302Last Call Requested-02Others
2012-04-21 .. 2012-04-2102Last Call Requested-00Others
2012-04-21 .. 2012-04-2102AD Evaluation-00AD
2012-04-21 .. 2012-04-2102AD Evaluation-00AD
2012-04-21 .. 2012-04-2102Publication Requested-00AD
2012-04-21 .. 2012-04-2102Publication Requested-00AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2012-04-21 but has not yet been approved, no final timing available.

The speculative analysis says that so far, the document has waited for AD 0 days, previous AD 0 days, authors 0 days, and others 13 days, a total of 13 days and was revised 1 times.

The (last) responsible AD for this document was Leiba_Barry.

Overall Processing Time Statistics

Document was in individual and WG process for 312 days, and in IESG/RFC Editor process for 13 days, 325 days in total. This is 0 years and 10 months.

Data Source

Original source data available in the tracker and draft history.