Document Processing Time Details for draft-ietf-appsawg-mime-default-charset

“End-to-End Delay from draft-smith to an RFC”

Document Timeline


IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

2012-05-15 .. 2012-07-0699RFC Ed Queue-0--
2012-05-15 .. 2012-05-1504RFC Ed Queue-0--
2012-05-15 .. 2012-05-1504Approved-announcement sent-0--
2012-05-14 .. 2012-05-1504Approved-announcement sent-0--
2012-05-14 .. 2012-05-1404Approved-announcement to be sent-0--
2012-05-10 .. 2012-05-1404Approved-announcement to be sent-0--
2012-05-09 .. 2012-05-1004IESG Evaluation-01Others
2012-05-09 .. 2012-05-0904IESG Evaluation-10Authors
2012-05-07 .. 2012-05-0903IESG Evaluation-22Authors
2012-05-07 .. 2012-05-0703IESG Evaluation-10Authors
2012-05-07 .. 2012-05-0703IESG Evaluation-00Others
2012-05-07 .. 2012-05-0703IESG Evaluation-00Others
2012-05-07 .. 2012-05-0703Waiting for AD Go-Ahead-00AD
2012-05-07 .. 2012-05-0703Waiting for AD Go-Ahead-00AD
2012-04-23 .. 2012-05-0703In Last Call-014Others
2012-04-23 .. 2012-04-2303In Last Call-00Others
2012-04-21 .. 2012-04-2302Last Call Requested-02Others
2012-04-21 .. 2012-04-2102Last Call Requested-00Others
2012-04-21 .. 2012-04-2102AD Evaluation-00AD
2012-04-21 .. 2012-04-2102AD Evaluation-00AD
2012-04-21 .. 2012-04-2102Publication Requested-00AD
2012-04-21 .. 2012-04-2102Publication Requested-00AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2012-04-21 and was approved on 2012-05-10.

According to the speculative analysis, the document waited for AD 0 days, previous AD 0 days, authors 2 days, and others 17 days, a total of 19 days, and was revised 2 times.

The (last) responsible AD for this document was Leiba_Barry.

Overall Processing Time Statistics

Document was in individual and WG process for 312 days, and in IESG/RFC Editor process for 75 days, 387 days in total. This is 1 years and 0 months.

Data Source

Original source data available in the tracker and draft history.