Document Processing Time Details for draft-eastlake-sha2

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2006-08-09 .. 2008-12-2399RFC Published-0--
2006-08-09 .. 2006-08-0999RFC Ed Queue-0--
2006-02-08 .. 2006-08-0999Approved-announcement sent-0--
2006-02-06 .. 2006-02-0899Approved-announcement to be sent-0--
2006-02-01 .. 2006-02-0699IESG Evaluation-05Others
2006-01-30 .. 2006-02-0199IESG Evaluation-11Authors
2006-01-18 .. 2006-01-3099IESG Evaluation-012Others
2006-01-18 .. 2006-01-1899AD EvaluationAD Followup00AD
2006-01-04 .. 2006-01-1899AD EvaluationRevised ID Needed014Authors
2005-07-31 .. 2006-01-0499AD Evaluation-0158AD
2005-07-31 .. 2005-07-3199Publication Requested-00AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2005-07-31 and was approved on 2006-02-06.

According to the speculative analysis, the document waited for AD 158 days, previous AD 0 days, authors 15 days, and others 17 days, a total of 190 days, and was revised 0 times.

The (last) responsible AD for this document was Housley_Russ.

Overall Processing Time Statistics

Document was in individual and WG process for 60 days, and in IESG/RFC Editor process for 373 days, 433 days in total. This is 1 years and 2 months.

Data Source

Original source data available in the tracker.