Document Processing Time Details for draft-daigle-rfc954bis

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2004-09-24 .. 2008-11-2899RFC Published-0--
2004-09-24 .. 2004-09-2499RFC Ed Queue-0--
2004-07-12 .. 2004-09-2499Approved-announcement sent-0--
2004-07-12 .. 2004-07-1299Approved-announcement to be sentPoint Raised - writeup needed00AD
2004-07-01 .. 2004-07-1299IESG Evaluation-011Others
2004-06-10 .. 2004-07-0199In Last Call-021Others
2004-06-01 .. 2004-06-1099Last Call Requested-09Others
2004-05-27 .. 2004-06-0199Publication Requested-04AD
2004-05-27 .. 2004-05-2799Publication Requested-00AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2004-05-27 and was approved on 2004-07-12.

According to the speculative analysis, the document waited for AD 4 days, previous AD 0 days, authors 0 days, and others 41 days, a total of 45 days, and was revised 0 times.

The (last) responsible AD for this document was Hardie_Ted.

Overall Processing Time Statistics

Document was in individual and WG process for 349 days, and in IESG/RFC Editor process for 117 days, 466 days in total. This is 1 years and 3 months.

Data Source

Original source data available in the tracker.