Document Processing Time Details for draft-crispin-imap-multiappend

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2003-03-20 .. 2008-11-2899RFC Published-0--
2003-03-20 .. 2003-03-2099RFC Published-0--
2003-03-20 .. 2003-03-2099RFC Ed Queue-0--
2002-11-08 .. 2003-03-2099Approved-announcement sent00--
2002-10-30 .. 2002-11-0899Approved-announcement to be sent008Others
2002-10-04 .. 2002-10-3099IESG EvaluationAD Followup026AD
2002-10-04 .. 2002-10-0499IESG Evaluation000Others
2002-10-01 .. 2002-10-0499IESG EvaluationRevised ID Needed03Authors
2002-06-14 .. 2002-10-0199IESG Evaluation-0107Others
2002-06-10 .. 2002-06-1499Waiting for Writeup-04AD
2002-04-25 .. 2002-06-1099In Last Call-045Others
2002-03-25 .. 2002-04-2599Last Call Requested-030Others
2002-03-21 .. 2002-03-2599Publication Requested-04AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2002-03-21 and was approved on 2002-11-08.

According to the speculative analysis, the document waited for AD 34 days, previous AD 0 days, authors 3 days, and others 190 days, a total of 227 days, and was revised 0 times.

The (last) responsible AD for this document was Freed_Ned.

Overall Processing Time Statistics

Document was in individual and WG process for 780 days, and in IESG/RFC Editor process for 364 days, 1144 days in total. This is 3 years and 1 months.

Data Source

Original source data available in the tracker.