Document Timeline
IESG Processing
The following table shows the events relating to the document during its IESG processing.
The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.
| PERIOD | VER | STATE | SUBSTATE | DISCUSSES | DAYS | RESPONSIBLE (Speculative) |
| 2005-06-21 .. 2008-11-28 | 99 | RFC Published | - | 0 | - | - |
| 2005-06-21 .. 2005-06-21 | 99 | RFC Ed Queue | - | 0 | - | - |
| 2005-04-01 .. 2005-06-21 | 99 | Approved-announcement sent | - | 0 | - | - |
| 2005-02-24 .. 2005-04-01 | 99 | Approved-announcement sent | - | 0 | - | - |
| 2005-02-17 .. 2005-02-24 | 99 | Approved-announcement to be sent | Point Raised - writeup needed | 0 | 7 | Prev AD |
| 2005-02-09 .. 2005-02-17 | 99 | IESG Evaluation | - | 0 | 8 | Others |
| 2005-02-09 .. 2005-02-09 | 99 | Waiting for AD Go-Ahead | - | 0 | 0 | Prev AD |
| 2005-02-08 .. 2005-02-09 | 99 | In Last Call | - | 0 | 1 | Others |
| 2005-01-11 .. 2005-02-08 | 99 | Last Call Requested | - | 0 | 27 | Others |
| 2005-01-11 .. 2005-01-11 | 99 | AD Evaluation | - | 0 | 0 | Prev AD |
| 2005-01-09 .. 2005-01-11 | 99 | Publication Requested | - | 0 | 2 | Prev AD |
IESG Processing Time Statistics
Document got to the AD/IESG on 2005-01-09 and was approved on 2005-02-24.
According to the speculative analysis, the document waited for AD 0 days, previous AD 9 days, authors 0 days, and others 36 days, a total of 45 days, and was revised 0 times.
The (last) responsible AD for this document was Hartman_Sam.
Overall Processing Time Statistics
Document was in individual and WG process for 648 days, and in IESG/RFC Editor process for 162 days, 810 days in total. This is 2 years and 2 months.
Data Source
Original source data available in the tracker.
|