Document Timeline
IESG Processing
The following table shows the events relating to the document during its IESG processing.
The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.
| PERIOD | VER | STATE | SUBSTATE | DISCUSSES | DAYS | RESPONSIBLE (Speculative) |
| 2004-09-29 .. 2008-11-14 | 07 | RFC Published | - | 0 | - | - |
| 2004-09-29 .. 2004-09-29 | 07 | RFC Published | - | 0 | - | - |
| 2004-06-16 .. 2004-09-29 | 06 | RFC Ed Queue | - | 0 | - | - |
| 2004-06-15 .. 2004-06-16 | 06 | Approved-announcement sent | - | 0 | - | - |
| 2004-06-15 .. 2004-06-15 | 06 | Approved-announcement to be sent | - | 0 | - | - |
| 2004-06-09 .. 2004-06-15 | 06 | Approved-announcement to be sent | - | 1 | - | - |
| 2004-06-09 .. 2004-06-09 | 06 | IESG Evaluation | Point Raised - writeup needed | 1 | 0 | Authors |
| 2004-05-27 .. 2004-06-09 | 06 | IESG Evaluation | Revised ID Needed | 1 | 12 | Authors |
| 2004-05-25 .. 2004-05-27 | 06 | IESG Evaluation | - | 1 | 2 | Authors |
| 2004-05-19 .. 2004-05-25 | 06 | IESG Evaluation | - | 0 | 6 | Others |
| 2004-05-18 .. 2004-05-19 | 06 | AD Evaluation | AD Followup | 0 | 1 | AD |
| 2004-05-14 .. 2004-05-18 | 05 | AD Evaluation | Revised ID Needed | 0 | 4 | Authors |
| 2004-04-30 .. 2004-05-14 | 05 | AD Evaluation | AD Followup | 0 | 14 | AD |
| 2004-04-01 .. 2004-04-30 | 03 | AD Evaluation | Revised ID Needed | 0 | 29 | Authors |
| 2003-11-06 .. 2004-04-01 | 03 | AD Evaluation | Revised ID Needed | 0 | 150 | Authors |
| 2003-11-03 .. 2003-11-06 | 03 | AD Evaluation | - | 0 | 3 | Prev AD |
| 2003-10-28 .. 2003-11-03 | 03 | Publication Requested | Revised ID Needed | 0 | 5 | Authors |
| 2003-09-11 .. 2003-10-28 | 03 | Publication Requested | - | 0 | 47 | Prev AD |
IESG Processing Time Statistics
Document got to the AD/IESG on 2003-09-11 and was approved on 2004-06-09.
According to the speculative analysis, the document waited for AD 15 days, previous AD 50 days, authors 202 days, and others 6 days, a total of 273 days, and was revised 3 times.
The (last) responsible AD for this document was Hollenbeck_Scott.
Overall Processing Time Statistics
Document was in individual and WG process for 602 days, and in IESG/RFC Editor process for 383 days, 985 days in total. This is 2 years and 8 months.
Data Source
Original source data available in the tracker.
|