Document Processing Time Details for draft-baker-liaison-statements

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2005-06-06 .. 2008-11-1405RFC Published-0--
2005-04-01 .. 2005-06-0604RFC Ed Queue-0--
2005-01-25 .. 2005-04-0104RFC Ed Queue-0--
2005-01-21 .. 2005-01-2504Approved-announcement sent-0--
2005-01-20 .. 2005-01-2104Approved-announcement to be sent-0--
2005-01-18 .. 2005-01-2003IESG EvaluationAD Followup02Prev AD
2004-12-13 .. 2005-01-1803IESG EvaluationAD Followup140Authors
2004-12-10 .. 2004-12-1303IESG EvaluationAD Followup23Authors
2004-12-09 .. 2004-12-1003IESG EvaluationAD Followup31Authors
2004-12-06 .. 2004-12-0902IESG EvaluationRevised ID Needed33Authors
2004-12-02 .. 2004-12-0602IESG EvaluationRevised ID Needed24Authors
2004-12-02 .. 2004-12-0202IESG Evaluation-20Authors
2004-12-02 .. 2004-12-0202IESG Evaluation - Defer-20Authors
2004-12-02 .. 2004-12-0202IESG Evaluation-20Authors
2004-11-30 .. 2004-12-0202IESG Evaluation-12Authors
2004-11-25 .. 2004-11-3002IESG Evaluation-05Others
2004-11-25 .. 2004-11-2502Waiting for AD Go-Ahead-00Prev AD
2004-10-25 .. 2004-11-2502Waiting for Writeup-030Prev AD
2004-10-11 .. 2004-10-2502In Last Call-014Others
2004-10-09 .. 2004-10-1102Last Call Requested-02Others
2004-10-09 .. 2004-10-0902AD Evaluation-00Prev AD
2004-10-07 .. 2004-10-0902Last Call Requested-02Others
2004-09-16 .. 2004-10-0702Publication Requested-021Prev AD
2004-09-16 .. 2004-09-1602AD Evaluation-00Prev AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2004-09-16 and was approved on 2005-01-20.

According to the speculative analysis, the document waited for AD 0 days, previous AD 53 days, authors 53 days, and others 23 days, a total of 129 days, and was revised 2 times.

The (last) responsible AD for this document was Carpenter_Brian.

Overall Processing Time Statistics

Document was in individual and WG process for 225 days, and in IESG/RFC Editor process for 265 days, 490 days in total. This is 1 years and 4 months.

Data Source

Original source data available in the tracker.