Document Processing Time Details for draft-alvestrand-ietf-mission

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2004-11-04 .. 2008-11-2899RFC Published-0--
2004-11-04 .. 2004-11-0499RFC Ed Queue-0--
2004-08-10 .. 2004-11-0499Approved-announcement sent-0--
2004-07-31 .. 2004-08-1099Approved-announcement to be sent-0--
2004-07-29 .. 2004-07-3199Approved-announcement sent-0--
2004-07-23 .. 2004-07-2999Approved-announcement to be sentPoint Raised - writeup needed06AD
2004-07-20 .. 2004-07-2399IESG Evaluation-03Others
2004-07-16 .. 2004-07-2099Waiting for AD Go-Ahead-04AD
2004-06-16 .. 2004-07-1699In Last Call-030Others
2004-06-16 .. 2004-06-1699Publication Requested-00AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2004-06-16 and was approved on 2004-07-29.

According to the speculative analysis, the document waited for AD 10 days, previous AD 0 days, authors 0 days, and others 33 days, a total of 43 days, and was revised 0 times.

The (last) responsible AD for this document was Kessens_David.

Overall Processing Time Statistics

Document was in individual and WG process for 128 days, and in IESG/RFC Editor process for 138 days, 266 days in total. This is 0 years and 8 months.

Data Source

Original source data available in the tracker.