Document Processing Time Details for draft-allen-fitsmime

“End-to-End Delay from draft-smith to an RFC”

Document Timeline

timeline

IESG Processing

The following table shows the events relating to the document during its IESG processing. The greyed out information is based on the substates and Discuss positions in the tracker. As not all ADs employ substates in the same way, and as all ADs employ them at least somewhat inaccurately, the data in this part of the table is very unreliable.

PERIODVERSTATESUBSTATEDISCUSSESDAYSRESPONSIBLE
(Speculative)
2005-04-26 .. 2008-11-2899RFC Published-0--
2005-04-26 .. 2005-04-2699RFC Ed Queue-0--
2004-11-02 .. 2005-04-2699Approved-announcement sent-0--
2004-11-01 .. 2004-11-0299Approved-announcement to be sent-0--
2004-10-24 .. 2004-11-0199IESG Evaluation-07Others
2004-10-22 .. 2004-10-2499Waiting for AD Go-Ahead-02AD
2004-10-22 .. 2004-10-2299Waiting for Writeup-00AD
2004-10-04 .. 2004-10-2299In Last Call-018Others
2004-09-27 .. 2004-10-0499Last Call Requested-07Others
2004-09-27 .. 2004-09-2799AD Evaluation-00AD
2004-09-10 .. 2004-09-2799Publication Requested-017AD
2004-09-10 .. 2004-09-1099Expert Review-00Others
2004-09-10 .. 2004-09-1099AD Evaluation-00AD

IESG Processing Time Statistics

Document got to the AD/IESG on 2004-09-10 and was approved on 2004-11-01.

According to the speculative analysis, the document waited for AD 19 days, previous AD 0 days, authors 0 days, and others 32 days, a total of 51 days, and was revised 0 times.

The (last) responsible AD for this document was Hollenbeck_Scott.

Overall Processing Time Statistics

Document was in individual and WG process for 9 days, and in IESG/RFC Editor process for 231 days, 240 days in total. This is 0 years and 8 months.

Data Source

Original source data available in the tracker.